ROUT:OPEN:ALL order

Posted: February 15th, 2012, 4:30 pm
by chrismu
Hello,
I'm using a 7706 switch card. When giving the command ROUT:OPEN:ALL, is there specific order in which the switches are opened.

Consider this case.
chan 1 - closed. wired to low impedance source
chan 11 - closed. wired to a differnt low impedance source.
chan 26 - closed. (In the position than isolates the "paired" channels 1 and 11 from each other.)

If I used ROUT:OPEN:ALL is there a gaurantee than chan 1 and or chan 11 will open BEFORE chan 26 opens. If chan 26 opens first, if would short chan 1 to chan 11 and cause havoc.

Thanks

Re: ROUT:OPEN:ALL order

Posted: February 21st, 2012, 2:11 pm
by Vince W
Hello chrismu,

I don't think there is a guaranteed order or timing for each switch opening in a multiple-open command. You would be best off opening them in an explicit (safe) order of sequence.